Redevelopment of Municipal Yacht Harbor

The proposed Breakwater Drive/Park Hazard Mitigation Plans were presented by the City of New Orleans' Department of Public Works and All South Consulting Engineers at the June 12, 2018 MYHMC Board Meeting:

Breakwater Drive Improvements Presentation (6/12/2018)

 

The Redevelopment of the Municipal Yacht Harbor was presented by the City's Capital Projects Administration, Moffatt and Nichol, and TKTMJ, Inc. (contractor) at the April 10, 2018 MYHMC Board Meeting:

MYH Redevelopment Presentation (4/10/18)

The City's  Capital Projects Administration issued the Notice-To-Proceed (NTP) to TKTMJ, Inc. on April 27th, and the contractor commenced construction on June 15, 2018.

 

As of June 21, 2017, the MYH Rehabilitation Project was in the Bid and Award Phase:

MYH Bid and Award Phase (6/12/17)

 

The project team accepted comments from the public in December of 2016. Listed below are public comments that have been received along with responses that have been prepared by the project team:

Response To Public Comments (1/13/17)

 

The Proposed Redevelopment of the Municipal Yacht Harbor was presented by the City of New Orleans' Capital Projects Administration and Moffatt and Nichol at the November 15, 2016 MYHMC Board Meeting, along with diagrams with dimensions of the existing and proposed fairways:

Municipal Yacht Harbor Presentation (11/15/16)

Existing Marina Fairways

Proposed Marina Fairways

 

The project team appreciates your participation in this exciting project.

 

 

Community Sailing